Business Operations Transformation

Our team proposed a project management office to support a growing business. I focused on how the work would be managed, how progress would be reported, and how risks would reach the right people.

University of Washington · Program Management and Consulting

Concept illustration for Business Operations Transformation

Project at a glance

Project type
Academic coursework · Graduate team project · Consulting proposal
My role
Developed the team proposal’s management approach.
Objective
Coordinate a growing business through a proposed PMO.
Key deliverables
Management structure, reporting cadence, risk-review approach, and team RFP response.
Tools / methods
Governance design, phased planning, KPI reporting, risk reviews.
Outcome / status
Academic proposal completed; PMO not implemented.

The problem

The case described a growing business with disconnected systems and inconsistent processes. The team needed a way to prioritize initiatives, coordinate work across departments, and give leadership a clearer view of progress.

My contribution

I developed the management approach covering the delivery structure, responsibilities, status reporting, and risk reviews. The full proposal was a team effort and also included discovery, change management, governance, and cost planning.

The work

  • Defined responsibilities across program leadership, project managers, and analysts.
  • Outlined weekly operational reports and monthly stakeholder reviews.
  • Connected quarterly executive reviews to milestones, issues, and decisions.
  • Described how the team would identify and monitor risks across workstreams.

How the solution took shape

  1. Start with the coordination problem

    Our team used the case requirements to frame a PMO proposal around disconnected systems and inconsistent processes. The proposed base-year sequence moved from discovery to PMO initiation and then optimization.

  2. Define who would make decisions

    For my management approach, I described a tiered structure with an executive sponsor, program manager, project managers, and analysts. The purpose was to distinguish strategic direction from day-to-day coordination and execution.

  3. Assign responsibilities to the work

    I connected the roles to initiative prioritization, timeline tracking, KPI reporting, process improvement, and the tools used to make performance visible. This made the organization model more useful than a list of job titles.

  4. Design reporting around the audience

    I outlined weekly status reporting on progress, milestones, issues, and immediate actions. Monthly stakeholder reviews would address workstream performance and KPI changes; quarterly executive reviews would focus on strategic updates and decisions.

  5. Build risk review into the proposed routine

    I proposed stakeholder input, planning workshops, and assessments of risk likelihood. The areas included change, technology, data, resources, and governance. Risk reviews were part of the reporting cycle so concerns could reach the appropriate decision makers.

  6. Bring the approach into the team proposal

    The management approach became part of the final RFP response alongside the team’s discovery, governance, change-management, and cost planning. The deliverable explained how the engagement would be run; it did not report an implemented PMO.

A closer look

The proposed 12-month PMO plan

Months 1–3

Discovery · 3 months

Months 4–8

PMO initiation · 5 months

Months 9–12

Optimization · 4 months

Review cadenceFocus
WeeklyProgress, risks, and immediate actions
MonthlyPerformance across workstreams
QuarterlyExecutive decisions and strategic updates
Proposed plan from the team RFP response and my management approach. The phases run in sequence for 3, 5, and 4 months; the review cadence applies throughout the proposed program. This is a delivery proposal, not completed client work.

An example from the work

The proposed reporting approach

Weekly reviews covered progress, risks, and immediate actions. Monthly reviews covered performance across workstreams. Quarterly reviews brought major decisions and strategic updates to executive sponsors.

The project in numbers

Proposal scope

12 months

Proposed base-year plan

The team planned discovery for months 1–3, PMO initiation for months 4–8, and optimization for months 9–12. These are proposed phases, not completed client work.

What came out of it

The team delivered an RFP response with a phased plan for establishing and improving a PMO. The proposal shows how I organize accountability and reporting around a shared delivery plan.

This project shows how I make a complex initiative easier to manage through clear ownership, reporting, and escalation.

Project scope and limits

Academic proposal, not an implemented client engagement. Proposed benefits, staffing, and costs are planning assumptions.